The timeline for this project is reflected in architecture section on Confluence as well and is as follows:
June 23rd - July 9th12th: Schematic Design
July 9th12th: Schematic Review Date
July 9th - July 12th: Minor Schematic fixes and checksJuly 12th: Schematic lock
July 12th - July 26th: PCB Design
July 26th: PCB Review
July 31st: Order PCB
Early F22 assemble boards with reflow and get them to firmware! Hopefully end of september!
ZP3 Arm/Disarm Controller Board - Michael Botros Daniel Puratich (Unlicensed)
...