The timeline for this project is reflected in architecture section on Confluence as well and is as follows:

  • June 23rd - July 9th12th: Schematic Design

  • July 9th12th: Schematic Review Date

  • July 9th - July 12th: Minor Schematic fixes and checksJuly 12th: Schematic lock

  • July 12th - July 26th: PCB Design

  • July 26th: PCB Review

  • July 31st: Order PCB

  • Early F22 assemble boards with reflow and get them to firmware! Hopefully end of september!