  • ~ July 9th

    • Assembly Start

  • July 9-12

    • created electrical harnesses

      • battery splitter

      • buck->pdb

  • July 15-17

    • determined working servos

    • fastened electrical components

    • mounted servos & motor

      • cut and bent wire for screw pin horns

      • mounted screw pin horns

  • July 18-19

    • troubleshooted receiver & video system

  • July 21st

    • this FT

Logistics

  • Sunday the 21st

  • Aiming for WRESTRC WRESTRC

  • Hoping to have all systems checked in the morning fully and fly in the afternoon

    • We have WRESTRC 11am to 6pm

  • Attendees

...