Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Fixed Wing

  • Timeline thoughts

    • Start manufacturing halfway thru the term.- Smile

    • Push pple to work faster, set realistic deadlines for projects. Check up on people more. - Smile

  • what’s needed from other subteams?

    • Patience. I think all avionics are finalized, so not much else needed. - Smile

Pegasus 2

  • What’s needed to finish it?

    • Attaching the landing gear to the x-frame

    • Pixhawk mount ready, need to 3D print stand-offs

      • Can we use those gummies here

    • print all electronic cases, ensure we have all bolts and nuts needed to mount PCBs

    • Weatherproofing needs to be manufactured. Thermoformed solution can be as heavy as 400g. Another option is to make a dome out of frame, maybe balsa wood or LW PLA and wrap the frame w plastic. I feel like we have to be realistic here and be willing to add minimum 300g.

      • Yea the extra weight is worth it for weatherproofing -Daniel

Tracking Ant

  • ready to FT?

    • Technically, yes. However, mech would like to do a design review to identify and fix some design problems

      • Proper supports to maintain the antenna’s pitch level

      • Baseplate not very steady. The normal vector of the top face of the plate can deviate from the yaw axis.

Thoughts on taller towers and new antennas

Work Sessions

  • Wanna go hard on the work sessions esp. on manufacturing side. Smile kinda slacked off during the summer because no manufacturing needed to b done and people can just work on CAD from home. People aren’t as involved when there aren’t work sessions. I can take the responsibility of running these sessions Saturday mornings - Smile

  • It’ll be easier with both of you onsite. -Daniel

  • Culture around nitpicks