Announcements

  • Range Test & Speed Test

    • Speed test has been descoped, just a range test on the ground

  • Autonomy Integration Test

...

Mechanical

  • Solutions for task 2

  • IMACS monitor mount almost done. Making sure there’s no interference w/ the switches when the case closes. The plate will likely be acrylic. Corner b

    • image-20241004-000200.pngImage Added

  • Pump Research and Integration

Electrical

  • Lighting Board Rev 3 blocked by LEDS

    • Should come any time now

  • Tracking Antenna EFS Handoff Status?

    • we only had components for 2 boards, both boards have assembly issues.

    • one board’s buck pad is damaged, now the plan is to fix on the other board

    • will apply the fix after hot plate arrives, assembly will most likely finish early next week

  • RPi Board Rev B assembly and testing status?

    • Assembled and in testing with autonomy

  • Video system installed

    • pending review

  • This weekend bringing up the single servo driver and reworking 6s servo module

...