Attendance

Mechanical

Notes on manufacturing status.

...

  • Fuselage status?

    • STATUS: Panels cut & mounted? (said would be done last weekend)

      • Panels are cut and ready to be mounted (planning to check how it fits with the wing/spars attached this weekend before fully mounting it)

      • image-20250129-002440.png

  • STATUS: Airframe slots (Mech/EE discussion last week)

    • Will be worked on this coming weekend

Wing

  • STATUS: Lasercut ribs (task was supposed to be given out last week)

    • Ribs were cut and ready to go

  • STATUS: 3D prints

    • One set of prints done

    • Need to print some parts for the aileron

  • STATUS: Frame (should be done), Wrapping (progress update)

    • Assembly and wrapping planned for next work session

  • Timeline: initial prototype within 2 weeks (~ Feb 8), bit more for maiden flight

    • UPDATE: still on target?

      • yes

landing gear

  • STATUS: (had some delays last week due to part orders and whatnot)

    • Anyone seen an amazon package w/ a servo adapter inside?

    • reach out on friday if this doesnt show up

      image-20250129-002534.pngImage Modified
  • Timeline: within next couple of weeks (~ Feb 1)

    • UPDATE: depends on order shipping, tentative ddl Feb 1

      • will be pushed back depends on machining status and the above servo adapter order

Empennage

  • STATUS: linkages for the elevators and rudder

    • haven’t started making the linkages but we have a plan. Should take couple hours.

  • STATUS: need to 3D print the elevator and rudder

    • Testing tolerance, should be ready by tomorrow to print the final rudder and elevators.

  • Timeline: within next couple of weeks (~ Feb 1)

    • UPDATE: still on target?

      • I think so, but some stuff will probably be worked on during Feb 1 work session. I am comfortable to pushing the deadline to Feb 8

...

Everything Mech is in last drawer in the red toolbox.

flagpoles are on 1st row on mech shelf

Avionics/EE updates

  • Maiden flight Electrical block diagram needs one more check before harness work starts https://uwarg-docs.atlassian.net/wiki/spaces/ARCHS22/pages/2556133415/Fixed+Wing+2025#Maiden-Flight-Electronics-System-Diagram

  • Jerry Tian to do last fix on harness diagram tn and assign out harness tasks

  • Harness timeline

    • physical harness done by Feb 23

  • 6s Servo Module

    • STATUS? (rev 2 pcb + efs update)

      • having trouble finding the module 😞

      • good amount of people assigned, Hardy Yu is leading it

  • 6s power module (EFS)

    • STATUS? (progress & setting deadlines)

      • person assigned is newer to embedded stuff, another person was added

      • being pushed in work sessions

      • having trouble flashing anything onto the board

      • sometime after midterms, IS BLOCKING EE HARNESS

  • STATUS: EE to finalize and order connectors

    • Sarah is placing the order

    • Order will be sent out tomorrow

Timeline

  • Foam Plane Pilot Training (first flight): Feb 2

  • Ecplise Eclipse Strapdown Test: March 1st/2nd

  • Eclipse Maiden Flight Test: March 8th/9th

Pilot Training - Foam Plane

  • Plane is built and validated on the ground

    • nylon lock nuts

  • Ready to test on the 2nd