  • STATUS: Harnessing (EE)

    • Jerry will lead eclipse harness work sessions

    • EE will work on comp critical projects first and then focus on eclipse harness

  • STATUS: 6s Servo Module / Single Servo Module (EE / EFS)

    • EFS

      Was able to run off DroneCAN commands

      from Pixhawk!
    • Dynamic node and neopixel LED are almost done

    • Will be tested this coming week

    • EE

      Need one 6S servo module (needs to finish being validated)

    • Two SSD (one works, other probably does according to Derek Tang will be tested)

    • need Xt60 breakouts, Jerry will order on amazon

  • STATUS: Electronics Validation

    • Pixhawk:

      • Has been flashed with Arduplane firmware

    • Servo validation

      • Will be tested in the coming week

      • test with SSD

      ?

    • Sensor validation

      • Both M9N GPS have been tested over DroneCAN

      • Manasva Katyal Will test compass, rangefinder, ep dual, esc, motor next week

      • Can also test pitot tube once tubing is cut and mounted

  • Thoughts on Nucleo breakout for ZP?

    • motor power and signal breakouts

    • built in sensors

    • signal connectors like zp dev interface

    • buck built in to power everythingTracking antenna V1 from 2023 and zp3 interface board already has a lot of the components from the above

  • bringup priority?

Pilot Training - Foam Plane

  • STATUS: RPC Laser Cutting Jerry Tian

    • Side Note: What are we planning to put on this plane?

      • Pixhawk, ESC+Motor, Servos, EP Dual

      • Anything else?

        nope

Timeline???

  • Eclipse Strapdown Test: Mar 27th (Thursday)

  • Eclipse Maiden Flight Test: Mar 29th (Saturday)

  • another foam plane: Mar 8th (Saturday)