Document containing plans for S24 Pegasus 2 bringup post-midterms.

Detailed plan:Refer to Big Quad 2025, https://uwarg-docs.atlassian.net/wiki/spaces/ARCHS22/pages/2249981953/2024+System+Architecture#Wiring-&-Outputs, Connector Standards

The mechanical frame of Pegasus 2 is very similar to Pegasus 1. The wiring will also be quite similar, but adjusted to follow the specs defined in Big Quad 2025.

The following block diagram is a high level representation of the current system architecture for Pegasus 2.

Drawio
mVer2
zoom1
simple0
inComment0
custContentId2558820629
pageId2556133403
lbox1
diagramDisplayNameBigQuad2025ConceptForElectronicsJune2024.drawio
contentVer4
revision4
baseUrlhttps://uwarg-docs.atlassian.net/wiki
diagramNameBigQuad2025ConceptForElectronicsJune2024.drawio
pCenter0
width1401.0000000000002
links
tbstyle
height728.5000000000002

Some notes on the above block diagram:

  • lighting boards CAN wiring dnp initially

  • dshot for escs through the pdb, no can, probably will never do CAN here, ESCs are right next to pixhawk and the CAN boards are extra weight complexity etc.

  • unified video system does not exist yet, wire up identically to peggy 1 and call it a day

Battery Harness Diagram

...

All connectors are xt90.

Session 1 (Wednesday July 10):

Plan:

...

Work completed:

  • ESC->PDB Dshot wiring complete

  • MT30s put on motors

    • Lengths roughly measured for motor->ESC wires, need to be cut+soldered

  • Battery harness design done, wires cut to length, two XT90s soldered

  • No work done on VTX, saved for next session.

  • No work done on PDB->Pix, saved for next session.

  • Note: Everything related to this session was put into the Pegasus 2 Frame box, with the frame. (located at the right side of second row of back shelf; behind EE shelf as of the time of writing)

Session 2 (Wednesday July 17):

Plan:

...

Work completed:

  • More battery harness XT90s soldered

Session 3 (Monday July 22):

Work completed:

  • Battery harness is almost complete. One more 3 wire joint to do.

...

  • Two of the motor to ESC had MT30’s soldered

image-20240723-010406.pngImage Added

  • No work done on VTX, saved for next session.

  • No work done on PDB->Pix, saved for next session.