  • Schem for both PCBs are completed and will stay pretty much the same (obv changes will be made if needed). The goal is to put both of these schems into a single project and create a new layout. Do whatever integration work is required in order to achive these

  • The approach for the management of this project will be:

    • Nolan Haines & Ahmed Osman are the PMs of this project. They will oversee the high level architecture, work distribution, and review contributions

    • a similar approach will be taken to how daniel did RPi interface. Individual members interested in this project will contribute to component selection & creation (as required), schem integration work, and layout work

    • the idea is to break the circuit into “modular” subsections that can be assigned to individual members to allow for interesting work for each of them while effectively getting the project done

    • work will be reviewed by PMs.

Action Item

Tentative Timeline

Actual Timeline (date compeleted)

Order TX modules

Feb 3

Order components for testing ELRS Gemini

Jan 30

(not doing this anymore)

Worksesh for changing and testing board

March 4

Power analysis done

Feb 7

Block diagram complete

Feb 7

Schematic complete

March 8

Assign layout tasks

After reading week

Architecture

To-do

Architecture:

  •  Create block diagram for architecture
  •  Research on whether we need an amplifier
  •