Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Meeting Scope

  • Track state of Cornflakes airframe post previous flight test

  • Identify and update deliverables, owners for each subteam for flight test next weekend

  • Look into long-term flight test planning (general flow of what we would like to ideally test)

Other Concerns

  • Track state of Icarus frame and when it will be ready for wiring

    • Cabin mounting of electronics, etc. should be ready

    • Can assemble frame and have it ready for wiring Friday

  • Concerns regarding onsite engineering bandwidth available re EE and EFS to wire and harness the droneIcarus

    • Lot of availability right after exam to work on Icarus

    • Will have to do harnessing during exams - not ideal

    • Harnessing will start during Easter long weekend

  • Lessened availability for flight test this weekend due to Easter and long weekend

Flight Test Outlook

Date

Note

April 8th

  • Continue transition validation and testing with new/redesigned system from mechanical

  • Continue remaining tests from previous flight tests (test RTL, etc.)

April 9th

  • Continue previous flight testing plan and complete as best as possible

  • (If 8th goes well) - Spend the day preparing Icarus for flight

April 16th

  • Hold for: Icarus Frame testing

  • CS2 on Cornflakes

  • Test out QR code based upload of waypoints re Task 1 on Houston

  • Plan out full path for waypoints Aidan Bowers (Deactivated) (SysInt’s already made comp-sim plan)

April 22nd

Comp flightline (if possible) run through

April 29th

1 week before comp - full systems check & second full comp flightline run through

Table of Contents
minLevel2
maxLevel7

April 8/9th

Subteam

Tasks (replace these w/asana links when you can)

Owner

Mechanical

Cornflakes modification for better propeller airflow

  • New Cabin

  • Pusher motor mount (move it aft)

Conall Kingshott

Alison Thompson

Electrical

Cornflakes Wiring modifications as required by system

Icarus Wiring: https://app.asana.com/0/1203349931374647/1204285821170041

Nolan Haines

Add telemetry for ESCs and pusher motor

Ethan Abraham

Hamza Ali

Sysint

End-to-end testing of system

Hamza Ali

Logistics

Logistics

  • ensure vehicles, submit FTR, verify bookings.

  • Submit flight test plan

  • Vehicle logistics

  • Ensure checklists are being followed

  • Fill flight box

Hardy Yu

Competition Frame (Icarus Aircraft)

Component

Tasks (replace these w/asana links when you can)

Owner

Mechanical

Update re latest date for readiness: 7-April-2023

  • Best estimate of readiness:

Conall Kingshott

Megan Spee

Electrical

Updates:

  • State of Icarus wiring diagram - Complete by 2-April(System Block Diagram)

    • RFC Created, not merged yet

    • One change to make - will be approved and merged by April-5-2023

  • Questions on power architecture and other follow-up from RFC re last week

    • Power architecture RFC Merged

  • Information: 2023 System Architecture

  • Develop system block diagram

  • Top-down physical electronics layout

    • Starting In its starting stages, working on referencing previous layout proposal

    • Will have RFC out by April-6-2023

  • SMEs:

Nolan Haines

Michael Botros

...