Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Meeting Scope

  • Track state of Cornflakes airframe post previous flight test

  • Identify and update deliverables, owners for each subteam for flight test next weekend

  • Look into long-term flight test planning (general flow of what we would like to ideally test)

Other Concerns

  • Track state of Icarus frame and when it will be ready for wiring

    • Cabin mounting of electronics, etc. should be ready

    • Can assemble frame and have it ready for wiring Friday

  • Concerns regarding onsite engineering bandwidth available re EE and EFS to wire and harness Icarus

    • Lot of availability right after exam to work on Icarus

    • Will have to do harnessing during exams - not ideal

    • Harnessing will start during Easter long weekend

  • Lessened availability for flight test this weekend due to Easter long weekend

Flight Test Outlook

Date

Note

April 8th

  • Continue transition validation and testing with new/redesigned system from mechanical

  • Continue remaining tests from previous flight tests (test RTL, etc.)

April 9th

  • Continue previous flight testing plan and complete as best as possible

  • (If 8th goes well) - Spend the day preparing Icarus for flight

April 16th

  • Hold for: Icarus Frame testing

  • CS2 on Cornflakes

  • Test out QR code based upload of waypoints re Task 1 on Houston

  • Plan out full path for waypoints Aidan Bowers (Deactivated) (SysInt’s already made comp-sim plan)

April 22nd

Comp flightline (if possible) run through

April 29th

1 week before comp - full systems check & second full comp flightline run through

Table of Contents
minLevel2
maxLevel7

April 8/9th

Subteam

Tasks (replace these w/asana links when you can)

Owner

Mechanical

Cornflakes modification for better propeller airflow

  • New Cabin

  • Pusher motor mount (move it aft)

Conall Kingshott

Alison Thompson

Electrical

Cornflakes Wiring modifications as required by system

Add telemetry for ESCs and pusher motor

Ethan Abraham

Hamza Ali

Sysint

End-to-end testing of system

Hamza Ali

Logistics

Logistics

  • ensure vehicles, submit FTR, verify bookings.

  • Submit flight test plan

  • Vehicle logistics

  • Ensure checklists are being followed

  • Fill flight box

Hardy Yu

Competition Frame (Icarus Aircraft)

Component

Tasks (replace these w/asana links when you can)

Owner

Mechanical

Update re latest date for readiness: 7-April-2023

  • Best estimate of readiness:

Conall Kingshott

Megan Spee

Electrical

Updates:

  • State of Icarus wiring diagram (System Block Diagram)

    • RFC Created, not merged yet

    • One change to make - will be approved and merged by April-5-2023

  • Questions on power architecture and other follow-up from RFC re last week

    • Power architecture RFC Merged

  • Information: 2023 System Architecture

  • Top-down physical electronics layout

    • In its starting stages, working on referencing previous layout proposal

    • Will have RFC out by April-6-2023

  • SMEs:

Nolan Haines

Michael Botros

...