Assembly Checks

...

  •  Verify no connector pins look soldered together

...

  •  Verify no pins on STM32 look shorted

...

  •  Verify all components for Flight 5.7V Variant are fitted

...

  •  Solder on radial capacitor for input buck

...

  •  Solder on test input leads for buck testing

...

  •  Verify pin 1 on chips aligns with indicator

...

  •  Apply a few plug/unplug cycles on connectors

...

  • to test solder joint quality

Power Testing

...

DMM

...

  •  Make sure no power rails are shorted to ground or each other with DMM

...

  •  Slowly increase voltage (with low current limit, 100mA max) on buck input, check its not drawing excessive current/power (ensure no output load)

...

  •  Probe the output net for voltage stability with DMM

...

  •  Slowly increase voltage on internal

...

  • 5V rail

...

  • and verify the internal

...

  • 3.3V rail turns on

...

Power Testing with Oscilloscope

  • (LDO functionality)

E-load

  •  Perform a load test on buck converter: use

...

  • an e-load to fully saturate the buck and verify you get the output current expected

...

  • (up to 1A)
  •  Step the load and perform efficiency calculations: 12V, 24V, 50V

...

Oscilloscope

  •  Load transient testing: Step the e-load and view the transient response from buck converter output.

...

  •  Battery inrush test: simulate hot-plugging a battery on the input terminal and view transient voltage spike/oscillations.

...

  •  Then, handoff to firmware for testing.

Firmware Testing

...

  •  Attempt to flash all boards

...

all leds functional

...

pwm output functional

...

CAN circuit functional

...

  •  Verify functionality of all LEDs
  •  Verify the PWM output
  •  Verify CAN circuit functionality
  •  Pixhawk servo CAN system test

...