Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Attendance

General Updates

  • New faculty advisor: Brandon DeHart

    • Manager of the RoboHub, and will be attending some of our competition syncs this term to provide technical guidance.

    • Derek Wright was too busy

  • Last flight test

    • Speed/Range/Obstacle avoidance

    • Did not test everything due to rain but some retune was done (needs more work)

    • Autonomy data collected

    • buck converter for RPi usb c port broke off

      • was untested

      • known issue with these board with respect to poor solder

  • Next flight test

  • Hotplate ordered - Order procurement sent out for hot plate, will be ordered imminently

  • Toaster oven not acquired yet - if you would like to help let me know

  • Get the electronsite role if on site - reach out to Ryan Scomazzon if you have issues

  • Can someone return the bmo5 connectors to Sarah’s office (E5 2104) - Andrew

  • Midterm board order coming up Nolan Haines .

  • Hot air gun broken - prob fixable?

    • If not see if we can get sponsored for a new one lol

    • Not blowing hot air??????

Reminders

...

Please update test plans/board documentation!

Board Name

status

blockers

plan going forward

Tracking antenna

assembled SMT components on 2 boards

  1. vin-gnd 200 ohm resistance issue

  2. fix shorted pins on the other pcb

continue debugging and document process

https://uwarg-docs.atlassian.net/wiki/spaces/Meetings/database/2752839681?entryId=8b156da0-b88f-4487-9034-999268a953df

ESC CAN

Assembled SMT components on all 5 boards

Resoldered some components that did not reflow well/had some minor issues (mainly the STM32)

Validated continuity + potential shorts, no perceivable issues so far

Added BM06 Connectors

EFS did some initial testing with the board (with more to come) and MCU is talking and working at the moment.

Waiting for EFS to do comprehensive test to ensure full functionality - needed for all 5 boards with only one being tested currently

Support EFS with anything needed/required on EE side of things

https://uwarg-docs.atlassian.net/wiki/spaces/Meetings/database/2752839681?entryId=2a9ce18b-e24a-5681-b816-b20145bf134e

LED Lighting REV3

Assembled 1 side (MCU + CAN circuitry)

Planning to do cleanup on STM32s

Cleanup on STM32’s done earlier today during work session

on Wednesday (writing this on Tuesday)

- no issues on validation side so far

Need NEOPIXELS to come in for the other side of the board

Wait for NEOPIXELS to come in ~2 weeks then assemble the other side

https://uwarg-docs.atlassian.net/wiki/spaces/Meetings/database/2752839681?entryId=7ceadf2b-7db2-51c4-b57b-f3eb3a499404

6S Servo Module

Planning on assembling during Wednesday work session - components sorted and ready to go

Assembled SMT components except for Neopixel for 1x 6s Servo board

no neopixel 😞

rework stm

https://uwarg-docs.atlassian.net/wiki/spaces/Meetings/database/2752839681?entryId=7f7d75da-97a5-4829-ae84-2f24de007591

GPS Breakout

Assembled

can’t find GPS board that needs to be soldered on, ask autonomy?

https://uwarg-docs.atlassian.net/wiki/spaces/Meetings/database/2752839681?entryId=e839dcd8-defc-42f1-8280-8e2c21fbeea5

Single Servo Driver

not started

https://uwarg-docs.atlassian.net/wiki/spaces/Meetings/database/2752839681?entryId=726878aa-bcb8-4728-9eed-18483cfb5c94

Bring-up Tasks

In order of priority.

...

Fixed Wing Updates - Fixed Wing 2025 - SysInt - WARG (atlassian.net)

  • Reminder: Our newest program

  • First arch sync of the term last week 2024-09-25 Fixed Wing Arch Sync - Meetings - WARG (atlassian.net)

  • Timeline: Finished end of term

  • Mech is cooking, see minutes

  • The below boards should be included

    • 6S servo module

      • would be worth rolling out an updated rev if we can to fix a minor issuemaking new rev to be ordered with midterm board order

    • Single Servo Driver

      • should be good, needs assembly.

    • 6S power module

      • highest risk

        • lowest necessity (RIP lol - Andrew)

    • CAN Integration 2025

Bootcamp Updates

  • Continue to pop off and ask questions in your bootcamp thread

General Tasks

In order of priority. These are the active design projects.

Potential new project: Standard connectors fixed wing

...

Potential new project: Test Automation

  • Needs Assessment (comparing to the manual test procedure we have rn):

    • 1. characterize our custom buck converter’s performance.

    • 2. understand our designs more, help ee members learn

      • Load transient test is helpful on identifying issues if downstream board is brownout during flight test

      • Knowing efficiency of the bucks

    • 3. efs running out of work to do

Action Items

...

  • Jerry’s is too busy to work on this rn, will be on hold until he is more free

Action Items

Jerry Tian will try to fix hot air gun, if not successful, he will write email to hakko for help