📋 Flight Preparation
Requested by: | Anthony Luo |
---|
Required Sub-team integration efforts | - Mech
- Electrical
- EFS
- Autonomy
- Operations
|
---|
Date of Request | |
---|
Location and Time | E7 1401 |
---|
Goal Summary | Full Spinup of pegasus |
---|
Approved? | Yes ✅ |
---|
👥 Mandatory Attendees
Name | Phone # | Role | Reason |
---|
| | Flight Test Lead | |
| | Pilot in Command | |
| | Safety | |
| | (Subsystems integration, Secondary pilot, etc) | |
👥 Auxilliary Attendees
🥅 Goals/Objectives
Objective ALL PROGRAMS RUN IN ACRO | Priority | Owner(s) |
---|
0-25-0 ramp | | |
0-50-0 Step | | |
0-100-0 Step Step input from 0-100% throttle, back to 0 after spun up. Checking for motor desyncs Checking for power monitoring brownouts knockoff criteria:- Current draw exceeding 80A Motor on-time exceeding 10 seconds Props loose issues / alarming observations. Re-asses and continue if safe
| | |
0-100-hold 5 seconds-0 | | |
sine wave ramping | | |
⏲️ Flight Test Timeline
Date/Time | Action |
---|
0X00 | Briefing @ WARG Bay |
0X00 | Arrival at Flight Test Location |
0X00 | Flight Test Operation #1…… (eg: Capturing data, tuning, etc) |
| Flight Test Operation #2 |
| Flight Test Operation #…….N |
0X00 | Debrief |
| |
| |
🧯 Incident Procedures
Incident | Location | Procedure |
---|
Fire | | |
Injury | | |
Property Damage | | |
🔧 Week-Before To-Do List
Week Before Checklist
SME Signoff
- Structures
- Fasteners Secure
- Motors secure
- Props secure (or instructions clear)
- Props clear (no chips)
- Harnessing
- No exposed contacts possible of shorting
- no loose cables
- Nothing tight / pulling
- power-up and motor-test completed
- No harsh edges that could potentially tear through wires
- Controls
- Pixhawk initial parameters configured
- RFD900 telemetry configured
- TBS Tracer Configured
- GPS configured
- Initial sensor calibration completed
- SD Card in drone, logging enabled
- Groundstation
- Mission Planner Setup
- RFD900 tower ready
- RC Controller channels, modes mapped and bound
System Testing Procedures
- Plan for harnessing drone in this document
- Flight test attendees noted
🔧 Day-Before To-Do List
Day Before Checklist
Batteries
- Plan for charging, discharging
- Sets tagged and ID’d
Test Procedures
- Procedures cleared, crew briefed and roles assigned
- Individuals clear on test plan
🚩 Pre-Spin-up Safety Checklist
- Drone is strapped, room is clear!
😎 Post-Flight Checklist
Item | Owner |
---|
- Use Flight-Post Mortem to Debrief
| ALL MEMBERS PRESENT |
- Discard of damaged batteries
| |
- Discharge used batteries for better longevity
| |
Flight Test Debrief
Flight Test Timeline
Analytics (hopefully applicable)
Flight Test Post Mortem // Final Thoughts // Condensed Summary
RCA for Red Items
Create a RCA and keep it as a child page.
Action Items
Other Resources
Booking WRESTRC Field
How to Book the Flight Grounds