Think about the follow categories when creating a list of risks: Technical: Requirements, Technology, Interfaces, Performance, Quality External: Customer, Contract, Market, Supplier Organizational: Project Dependencies, Logistics, Resources, Budget Project Management: Planning, Schedule, Estimation, Controlling, Communication |
Create a list of risks applicable to the project. I'll start you off
Part delivery is much slower than expected, pushing back testing and therefore project deadlines
Members miss deliverable due to increased work load
Schedule didn’t allow for multiple iterations to occur, now we’re stuck with a less-than-ideal product
...
The risk score is based on two axis, Probability and Impact. Use the following chart to understand where a risk falls based on these two factors. |
SEVERITY | |||
---|---|---|---|
PROBABILITY | ACCEPTABLE | TOLERABLE | EXTREME |
IMPROBABLE (0%-30%) | Score: 3 (low) | Score: 15 (low) | Score: 30 (Medium) |
UNLIKELY (30%-60%) | Score: 6 (low) | Score: 30 (Medium) | Score: 60 (High) |
POSSIBLE (60%-80%) | Score: 8 (low) | Score: 40 (Medium) | Score: 80 (Extreme) |
PROBABLE (80%-100%) | Score: 10 (Low) | Score: 50 (High) | Score: 100 (Extreme) |
Use the following table to analyze each risk brought up in the “Risk Identification” stage |
Risk Event | Related Subteam | Probability % (P) | Severity Rating (S) | Risk Score (P*S) |
---|---|---|---|---|
Sub-team XXX delivers task 7 days late which delays the overall project by 7 days. | XXX | Probable (90%) | Extreme (100) | High (90) |
Any “High” or “Extreme” risks should have an action plan to mitigate any impacts. “Extreme” risks should also have layers of redundancy. |
Risk Event | Risk Response | Assignee (RSE) |
---|---|---|
Sub-team XXX delivers task 7 days late which delays the overall project by 7 days |
| @Julia |
What risks actually happened? Document them and add them to the risk analysis for insight on future deadlines. |
Risk Event | Risk Impact | Future Mitigation |
---|---|---|