Project UNTITLED: Test Quad Plane, page WIP
Teams | Mechanical, EFS, Sysint |
---|---|
Integration Owner(s) | @Aidan Bowers (Deactivated) |
Project Owners | @Megan Spee |
Contributors | |
Stakeholders | @flight testers |
Objective | Design, build, iterate on, and test a line of quad planes that meet the list of requirements below |
Due Date |
|
Problem Statement
Project Details
Timeline Version 1
Feb to June, reasonable for a 3-8 person team
NOTE I FORGOT ABOUT READING WEEK/MIDTERMS WEEK
Timeline Version 2
Feb to Aug, lax
Milestones and deadlines
Milestone | Owner | Deadline | Status |
---|---|---|---|
Prelim meetings, PKO | @Megan Spee | Feb 13 | At Risk |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|