6-Week Comp Drone Timeline
Week | Objectives | Results/Updates |
---|---|---|
Week 1 | Full CAD assembly complete enough for a CAD review on oct 30th Finding suppliers for carbon fibre Planning manufacture/ materials |
|
Week 2 | System architecture meeting! Finalizing CAD assembly based on architecture meeting: props, motors, batteries, servos Mass calculations Begin manufacture of frame, acquire CF Final CAD revision for nov 6th |
|
Week 3 | Build superstructure. This means wings, booms, horizontal stabilizer, motor mounts, line everything up and make sure it fits IRL. Fuselage model might not be manufactured (CF supply when). |
|
Week 4 | Continue building superstructure. Add internals when we have them: clear up some vague CAD, like landing gear, door hinges, anything small that depends on other things. CF manufacture if materials are ready Evaluate progress and update timeline if necessary |
|
Week 5 | Assemble the plane and finalize calculations to do with mass, CoG, etc.
|
|
Week 6 | Test flights |
|
Week 7 | Start of week: aircraft is complete! good luck on exams! |
|