2023-07-27 EE Meeting
General Team Status/Schedule:
Meeting times:
EE Meeting: Thursdays 7-8 PM EST E5 2103
Leads Meeting: Thursdays 9-10 PM EST E5 2103
Team Competition Aircraft Sync: Monday 7:30-8:15 PM
Attendance:
In Person | Online |
---|---|
Michael Anni Parker Zen Neel Jerry |
|
Updates this week!
Admin
No work session this weekend
Push wiring diagram project (we want to start assembling electrical at end of the term/beginning of next term)
Need 1-2 people who will be onsite next term to represent WARG EE at the Engineering Orientation on September 7th from 5-7pm
Nolan
Mena (maybe)
Last EE meeting for the term
Who is interested in electrical assembly? (2nd Half of August)
Neel
Parker
Farris (2nd last weekend of August)
Nolan
Mena (after 25th)
Michael
Zen (until 25th)
Jerry and Nolan interested in RF
Look into getting Network/Signal Analyzer
@Michael Botros to follow up with this
Active PCB Projects
High Current Power Module (Zen, Chris)
Updated 12V buck based on feedback. Finished component selection for 5V buck.
Schematic review perhaps next week
@Michael Botros read through confluence
12S ESC (Ethan, Chris)
Sourcing buck components
Onboarded Saksham onto project
Chris has symbols and footprints that need a review, Ethan will get on this
Board 100% isn’t being completed this term. Realistic is that we’re ordering by end of Sept, assembling and bring-up will go to mid-Oct, and then integrating with FOC firmware will be late next term and will carry into Winter term
6S ESC (Mena, Rayyan)
Rayyan: Continuing to go through datasheets to source passives
Mena: Shifting focus on drone wiring for now
LED Controller (Neel, Parker)
Finalizing the block diagram tonight.
ELRS Gemini (Michael, Farris)
Michael
No real progress this week from me
Farris
Layout grind, placement done and a lot of routing done, mainly the more complicated parts (RF, power, ESP fanout)
Responded to @Daniel Puratich's comments & suggestions, will have to follow up on some of those action items though
PDB (Tom)
@Michael Botros needs to check in with Tom
Tracking Antenna (Nolan, Hardy, Rukshi)
Rukshi and Hardy going strong
Buck selection for 5V rail in question
12S Servo Module (Stanley, Jack, Jerry)
Stanley: Selected new input capacitors, added new components to to Altium project, (had to download and modify footprints for Al poly, and 2220 caps, please look over them)
Jack: Working on sourcing TVS diode for overcurrent protection boards
Jerry: need to finalize switching FET. Added DNP pads on schematic.
Drone Wiring
Choosing wires and connectors
Order going tonight
Pixhawk and peripheral connectors priority next
Bootcamper Progress Updates
No bootcampers currently