2024-11-17 EE leads:PMs sync

Attendance:

@Ryan Scomazzon

@Andrew Chai

@Meghan Dang

 

Board Bringup Priority List:

  1. Water Controller Rev 1 - this term

  2. LED controller rev 4 - this term

  3. Tracking Antenna Rev 2

  4. 6S Servo module rev 2

  5. Unified VTX

  6. Water Controller Rev 2

  7. Sensor Cluster

  8. Programming Connector Adapter - this term

    1. assemble w/ water controller bc both small boards

 

Coop Boards:

  • 12-5V @ 4A Buck w/ ELRS

  • USB-C Sink

  • 24V-5V @ 5A Buck

    • ask if they need more hands to assemble these

 

Worksessions:

  1. assemble

    1. 3x water controller

    2. 2x programming conn header (since two small boards can take up a work session)

  2. validating water controller and program conn header

  3. LED controller ??? unlikely bc finals

Possible Dates:

  • Friday Nov 22nd

  • Sunday Nov 24th

  • Wednesday Nov 27th - maybe, depends on how busy we are

  • Friday Nov 29th - again depends

  • Sunday Dec 1st - probably not happening