Task Description
Currently, our EP2 board (which establishes ELRS connection to allow remote control of the drone) is taped to the top x-frame plate. We want a better way to secure EP2.
The task is to design an enclosure which will shield EP2 and secure it properly onto the x-frame plate.
Constraints
Constraints | Written By | Append Date |
---|---|---|
ELRS antennas must be exposed | June 12, 2024 | |
Hole/slot for power cable | June 12, 2024 | |
Passive cooling by airflow | June 16, 2024 | |
Mounts to a 30 x 30 grid pattern |
Relevant Contacts
Subteam | Contact | Contact Description |
---|---|---|
Tech Director | Answer questions regarding EP2 and add constraints if needed |
Assignees
Assignee | Asana Task | Date |
---|---|---|
link to asana task assigned | Date assigned |
Task Progression/Updates
Author: Pranav Bommireddipalli Date: 2024/06/25
Created Initial Design