2024-11-28 Comp Arch Sync

Attendance

  • @Daniel Puratich

    • I have a presentation for 20% of my grade (not throwable) in a course for the first 30 mins of this sync, will try to make it as soon as possible.

  • @Nathan Green driving meeting

  • @Smile Khatri

  • @Evan Janakievski

  • @Alison Thompson

  • @Andrew Chai

  • @Georgia Vachon Westerlund

  • @Megan Spee

  • @Meghan Dang

  • @Tim Gu

  • @Maxwell Lou

  • @Kenny Na

  • @Omer Sajid

  • @Anthony Luo

  • @Derek Tang

  • @Sohee Yoon

Mechanical

  • status of both task 2 solutions

    • will be done this weekend

  • Houston Motors status

    • Haven’t been ordered. Waiting for decision if we are switching to 6s or keeping 3s and what new form factor of motor should be

    • Will order Dshot ESCs too @Nathan Green

Autonomy

  • what is plan for making the system work next term?

  • what are min viable product milestones?

  • when do we want to deliver minimum viable system?

  • IR camera driver and detection almost merged in, 90% of the way there

  • IR camera settings: Max ISO is 64 and doesn’t look too grainy

  • MAVLink communication to ground is in progress

    • FTP has some hope (can see files, but need some more work on reading)

    • StatusText has been debugged and working (on sim)

  • Pegasus killswitch and UART setup complete (although killswitch not set on controller)

Electrical

  • ssd status

    • done ee-wise - it worky :))))

    • We will probably validate some more next term so we have extras

      • make 3 more next

  • water controller status

    • assembled, validated, and tested, handed-off to mech

  • programming board

    • will be rlly useful for led board validation

    • will be assembled sometime before end of term - as soon as digikey components come in (likely tomorrow or monday)

  • No more bring up sessions this term - what has been done is where we are standing for this term

    • Ryan and Kenny still onsite and no finals if something urgent is needed

  • We plan to get our next board order out beginning of next term.

    • Comp relevant boards

      • Water controller rev2 is the main target here - one more channel for driving valve if needed

        • Question for mech - does it look like we are still gonna need this?

      • Pi interface rev C

  • board bring up plan for next term

    • Water controller rev2 when it comes in

    • LED controller rev 4 - didnt end up happening this term

    • Tracking Antenna Rev 2

    • 6S Servo module rev 2

    • More Single servo drivers

  • wiring

    • video system wired yesterday

    • should be fine

EFS

Flight Testing

  • what are we flying this weekend?

    • Plan is only Pegasus as Houston motor issues and replacements have not been ordered

    • Daniel proposed not flying this weekend and waiting for Dec 14th flight test to test landing gear

    • Don’t fly this weekend, wait for the 14th

  • what needs to be done to be ready for mid december FT?

    • Water bucket design and implementation

  • directors should try to timeline next term with FTCs.

    • We should keep the testing program going leading up to comp.

Asana

  • Update all deadlines, add in new critical tasks

Comp Logistics

  • how will we transport drone?