Meeting overview

Meeting to discuss state of Competition Aircraft big quad.

  • Timeline recap

  • Integration recap

  • EE Clarity

🫂 Attendance


🗒️ The Weekly Recap


✈️ Flight Tests:

  • Autotune works. well.

📦 New arrivals

✅ Open action items


Conall Kingshott Composites stuff never properly setup, not a problem that we had not given to him, Graeme figuring everything out and then letting us know. Composite manufacturing in the next two weeks.

#electrical: Crimps, connectors, housings, signal analyzers, etc.

📝 Meeting minutes


Frame Updates 🚁

MECHANICAL

Composites in the next two weeks, before midsun gets it in (midsuns stuff is massive and takes a while)

  • Try and get as many people in the room as possible.

Frame updates

  • Starting on landing gear prints

  • MCMaster Carr order for standoff stuff & miscellaneous items.

  • Talking to Les (machinist). Will likely have to do a lot of this ourselves and then send it off to him to finish (battlebots causing issues).

Sensor Updates 📏

  • RTK GPS? Has antenna and control box.

    • One M9N, one RTK.

    • Mechanically identical, mounting pattern is the same.

    • will remain on posts (similar to vanny, except further).

RF updates 🌐

  • Need notch filters? 5W video very much stepping on other freqs? not sure…. currently investigating

  • Could get SDRPlays. (RSP1A → to be acquired)

Motor 3-phase connectors

MECHANICAL ELECTRICAL INTEGRATION

Battery PDB Distribution (question)

ELECTRICAL

  • How are batteries going to be arranged in series/parallel?

    • Scuffed diagram that needs explanation of potential implementation for three 12S batteries

  • How will our board support this layout?

  • Thoughts:

    • 2 PM02D’s (2 banks of batteries), parallel after. Potentially on either side of the battery.

    • Junction point closer to the edge of the board (away from the pixhawk).

Airside Electrical Layout (error)

ELECTRICAL MECHANICAL INTEGRATION

  • Where each component goes needs to be added to the architecture document.

  • Need selection of proper wire gauges, types, etc.

    • https://www.engineeringtoolbox.com/wire-gauges-d_419.html

    • For Battery connections, 8 AWG can be used to handle 75A continuous (maybe a little lower if stranded)

      • Stranded likely needed in order to have the required flexibility

      • Two power modules in parallel, two banks of batteries in parallel.

    • For motor connections, each motor draws around 15A (determined when discussing MT-30s)

      • 14 AWG wire (24A) should be enough for ESC connections to PDB

  • Wire gauge for sensors

  • Crimpers

  • No labels