Date | Gimbal | Grabber | Frame | General Tasks |
---|---|---|---|---|
Jan 4 |
|
|
|
|
Jan 11 Report due Jan 14 |
|
|
|
|
Jan 18 |
|
|
| |
Jan 25 |
|
|
| |
Feb 1 |
| Milestone: finish design for frame
| ||
Feb 8 | Milestone: finish design for grabber
| |||
Feb 15 |
|
| ||
Feb 22 | READING WEEK | |||
Mar 1 | MIDTERM WEEK | |||
Mar 8 | ||||
Mar 15 | Milestone: Final assembly | Milestone: Final assembly | Milestone: Final assembly | |
Mar 22 | Flight testing | Flight testing | Flight testing | |
Mar 29 | Flight testing | Flight testing | Flight testing | |
April 5 | Competition ready | Competition ready | Competition ready | |
April 12 | FINALS | FINALS | FINALS | FINALS |
April 19 | FINALS | FINALS | FINALS | FINALS |
April 26 | Final tweaking | Final tweaking | Final tweaking | Final tweaking |
May 3 | COMPETITION WEEK | COMPETITION WEEK | COMPETITION WEEK | COMPETITION WEEK |