🛸 General Team Status/Schedule (inc. other subteams):

  • Bay cleanup (thanks Daniel)

  • Gordon + Tony + Aidan + Dhruv prepped for flight test today

🔗 Quick Links:

Table of Contents

🖥 PR’s and Reviews

  • Hardfault Shutdown in PR. Waiting for hardware testing.

  • PID Threads PR (David)

  • PathMan PR (Neha)

Updates this week!

(Updates here → see table of contents for structure)

✈ Priorities next week:

  • SF port - almost done (~ 50%, mostly linker).

  • Telemetry Working on ZP Port.

😅 STUCK!

🍍 Team Member Updates

Anthony L

  • On SF

  • working on bay organization plans

Gordon

  • Flight Testing Schedule, aiming for pix flights once new frame iteration built.First Phoenix Flight Tonight

  • Plan next Phoenix flights

  • Misc. On-site testing as people need

Aadi

  • went through and recorded all of our xbees, and their freq and range, and addresses

  • started python driver for ground station (not sure what repo to put it in)

Dhruv

  • Helped JJ and David regarding their respective tasks, conducted some re-architecting for a gimbal module thread

  • Worked on implementing singleton with LOS_Position, LOS_Link

Tony

  • Porting telemetry manager

    • Made LOS interface for Comms and Telem. (Needs to be converted to singleton)

Neha

David

  • PID thread testing still in progress

  • Stuck in Hal_delay() because tick isn’t updating/systick handler needs to be implemented

JJ

  • Working on Gimbal refactoring

  • Meeting with Chris at next in person work session to discuss RC Emulator

Maureen

  • bootcamp is going ok?

Shahithya

  • still working on bootcamp

Chris

  • Talked with JJ about emulator, discussed implementation plan

  • Wasn’t able to finish VN300 driver bec of a school lab I spent way too much time on

    • DEFINITELY will finish by this week to start testing

🔭 Things to look out for!

  • crying…. 😞