🖥 PR’s and Reviews
Hardfault Shutdown in PR. Waiting for hardware testing.
PID Threads PR (David)
PathMan PR (Neha)
❗Updates this week!
(Updates here → see table of contents for structure)
✈ Priorities next week:
SF port - almost done (~ 50%, mostly linker).
Telemetry Working on ZP Port.
😅 STUCK!
🍍 Team Member Updates
Anthony L
On SF
working on bay organization plans
Gordon
First Phoenix Flight Tonight
Plan next Phoenix flights
Misc. On-site testing as people need
Aadi
went through and recorded all of our xbees, and their freq and range, and addressesstarted python driver for ground station (not sure what repo to put it in)
Dhruv
Helped JJ and David regarding their respective tasks, conducted some re-architecting for a gimbal module threadWorked on implementing singleton with LOS_Position, LOS_Link
Tony
Porting telemetry managerMade LOS interface for Comms and Telem. (Needs to be converted to singleton)
Neha
David
PID thread testing still in progressStuck in Hal_delay() because tick isn’t updating/systick handler needs to be implemented
JJ
Working on Gimbal refactoringMeeting with Chris at next in person work session to discuss RC Emulator
Maureen
bootcamp is going ok?
Shahithya
still working on bootcamp
Chris
Talked with JJ about emulator, discussed implementation planWasn’t able to finish VN300 driver bec of a school lab I spent way too much time onDEFINITELY will finish by this week to start testing
🔭 Things to look out for!
crying…. 😞
Flight Test Final Prep
Phoenix First Flight (After the meeting)