changes.mady.by.user Jinghao Lei
Saved on 2022-07-13
...
Time
Item
Presenter
Notes
phonenix
FW do crash tests, be able to replace the legs
Mech team doing recap
didn’t do altitude hold
timeline is behind schedule, but at least a flight, July 8th for pid tuning, delayed because of midterm, and boards.
buying something off the shelf instead of ordering custom ones? (not a good idea)
ZP3
schematic almost done
schematic review ongoing
do we want to USB to be on the board? (probably no, whatever is easiest)
deadline: Sept 1st, 5 boards. fw is mostly on neucleo, needs to be ported to new ZP3 PCB, estimated to take 2 days to 2 months (lmao)
need ppl to solder/assemble ZP boards (we might now have enough people) (recruiting season as well)