Topic

Notes

Data Telemetry


GUI

  • Subtasks assigned, work started

  • Altitude controller and logging page done

  • Map, motors page in progress

  • Subtask meeting scheduled

  • Deadline: November 5th

Landing pad

  • Tasks assigned

  • decided on yolov7

  • looking for training data

  • model setup

Met on 10/29:

  • found/finalized data sources for training

  • have working YOLOv7 model + tested model

To-do:

  • Compile the trees/obstacles dataset

  • Train on YOLOv7

  • get landing pad photos

Path Optimization

  • Research stages

  • Goal for this week to collect research papers, decide framework

Auto Landing

  • Jetson set up

  • Confluence doc for data processing to EFS ready

  • research into distance

  • venv issues on jetson

Autonomous Landing R&D

...