Current Must Haves: |
|
---|---|
Future Expansion: |
|
Not in scope: |
|
🫠 High-Level Flowchart
...
This is the rough idea of how it is gonna work
please point out the flaw in this type of design and the missing part of the system
🗓️ Timeline
The goal is to have the first flyable prototype done in mid-June. The actual time span can be longer since there will be a lot of components involved and they all need testing and debugging. The good part is that Hardy Yu has enough time to invest in this development since he is the coop.
...
🫠 High-Level Flowchart
...
This is the rough idea of how it is gonna work
...
🚩 Milestones & Deadline
Mileston | Owner | Deadline | Progress |
---|---|---|---|
Class structure design | May 12th | ||
PPM | May 21th | ||
MAVlink | May 21th | ||
SM Coding | May 26th | ||
Integration & Testing | May 9th | ||
Houston Flight Test | June 10th |
...