Updates from E2E flight test on March 30
Flight test on April 6 - Comp Sim 2!
Team social on Friday
From Mihir Gupta
Thank you guys for all the hard work this term. Looking back we got a lot done this term and its all because of the effort you guys put in!
Sorry for the delay in PR reviews, will try to get thru them soon
Project Updates
Airside System
PR for geolocation worker submitted by Dylan Finlay
PR for logging submitted Tong Zhang
Pathing
From Mihir Gupta: We need to create ticket to get Task 2 ready for comp (minor adjustments but critical)
Remove Landing Zone B (LZB) from comp CSV file
Create a module that will append takeoff and loiter (lots of examples of takeoff and landing but we don’t have one for loiter)
LTE
Maxwell Lou PR is up for image decode
Jonathan Yuan PR is up for socket wrapper
From Mihir Gupta: Can I get an update on the status on image encode?
Model Training
Decide on augmentations after today’s meeting