Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

🛸 General Team Status/Schedule:

  • Meeting times:

    • EE Meeting: Monday 8-9 PM E5 2103

    • EE Work Sessions: Tuesdays 7-8PM E5 2003 (The Bay)

    • Icarus Sync: Tuesdays 9-10pm E5 2004

    • General: Thursdays 8-9 PM E7 5343

  • Project Updates Discussed in the meeting!

  • LAST Formal Electrical Subteam MEETING BEFORE EXAMS

Attendance:

🍍 Updates this week!

Cornflakes

April 2 Flight Test

  • Manufactured all required battery harnesses for the flight test

  • Got Michael’s buck board going for the telemetry tower

Icarus Wiring Diagram + Harnessing

  • Icarus wiring diagram RFC created and almost ready to merge

  • Progress on layout diagram with Mena, Nolan, Michael and Rayyan

  • Power architecture RFC merged.

EE Onsite Work Session

ZeroPilot Program

  • No progress due to flight test taking priority

Admin

PCBs

24-12,5 Buck (Ethan, Michael)

  • 4 buck converters completely assembled for telemetry

  • See Asana for timeline

12-5 Buck (Nolan)

  • Design completed, awaitting order, see Asana for timeline

5-24V Boost (Steven)

12S Servo Module (Stanley, Michael, Rayyan)

  • Michael: Fixed some small schematic things for overcurrent protection and I/O pages

  • Stanley: Almost finished buck schematic, footprint for mosfet and diode required

4S Motor Controller

  • Kevin: Will provide a PCB layout review tonight

Bootcamper Progress Updates

  • Kevin Li:

    • Reviewed Michael and Farris' sections

    • Should I reach out to you both for changes I think would be appropriate to make? Or should I just do them without asking

  • Robson - Did not come in person due to sickness; done bootcamp just need to schedule meeting w/ Michael

  • Tom - Finished bootcamp, doing review after ee meeting with Michael