Mechanical

  • Motor and propellers have arrived. Motor mount to be adjusted accordingly.

  • Manufacturing started last week. The progress so far:

    • All plates for the frame have been waterjet

    • Finished few stand-offs for the frame + 1 wing-spar

  • Plan for this weekend:

    • Waterjet the landing gear

    • Finish the second wing spar and tail boom (should be achievable this Saturday)

  • Empennage design complete, balsa sheets, and wooden dowels need to be procured (that’ll happen this week)

    • using 2 servos for the elevator, 1 servo for the rudder. They have been ordered already.

  • Nathaniel Li Wing manufacturing timelines?

    • Can get started on 1 of the wings this weekend since the spar is done

Avionics

  • What is readiness of all of the following boards!

...