Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  •  Verify the 5V output rail turns on (buck functionality)
  •  Verify the internal 3.3V rail turns on (LDO functionality)
  •  Slowly increase voltage (with low current limit, 100mA max) on buck input
  •  Check for excessive current/power draw (ensuring no output load)
  •  Optionally, measure potential when EN pin activates buck IC
    •  Varies due to hysterisis, but ~5.2V
  •  Probe the output net for voltage stability with DMM

...

E-load

  •  Perform basic load test on buck converter: use an e-load to fully saturate the buck and verify you get the output current expected (stepping the load up to 4A)saturate a 5V line to 0.8A

Oscilloscope

  •  Load transient testing: Step the e-load and view the transient response from buck converter output.
  •  Battery inrush test: simulate hot-plugging a battery on the input terminal and view transient voltage spike/oscillations.

...