Meeting overviewMeeting to discuss state of Competition Aircraft big quad.
|
Table of Contents |
---|
🫂 Attendance
Daniel
Michael
Nathan
Conall
Arjun
Megan
Anni
Mena
Neel
🗒️ The Weekly Recap
✈️ Flight Tests:
Vanny SUCCESSFULLY completed auto-tune
Noticed thrust loss on Motor 3 after Battery Failsafe → Investigation ongoing.
This is (not) expected behaviour.
CV Landing pad detection works.
RTK GPS not tested .airside
works on the ground
📦 New arrivals
HERE RTK GPS Base stations here.
Carbon Fiber tubes here.
✅ Open action items
@Mech to send EE basic X-frame layout so that EE can come up with wiring diagrams/channels.
@Anni to look at static load testing
Conall Kingshott look at talking to bryan about composites Composites stuff never properly setup, not a problem that we had not given to him, Graeme figuring everything out and then letting us know. Composite manufacturing in the next two weeks.
📝 Meeting minutes
Frame Updates 🚁
Status | ||||
---|---|---|---|---|
|
Composites in the next two weeks, before midsun gets it in (midsuns stuff is massive and takes a while)
Try and get as many people in the room as possible.
Frame updates
Starting on landing gear prints
MCMaster Carr order for standoff stuff & miscellaneous items.
Talking to Les (machinist). Will likely have to do a lot of this ourselves and then send it off to him to finish (battlebots causing issues).
Sensor Updates 📏
RTK GPS? Has antenna and control box.
One M9N, one RTK.
Mechanically identical, mounting pattern is the same.
will remain on posts (similar to vanny, except further).
RF updates 🌐
Need notch filters? 5W video very much stepping on other freqs? not sure…. currently investigating
Could get SDRPlays. (RSP1A → to be acquired)
Motor 3-phase connectors ✅
Status | ||||
---|---|---|---|---|
|
Status | ||||
---|---|---|---|---|
|
Status | ||||
---|---|---|---|---|
|
3-phase connectors decided:
MT-30 for inner-hub-to-tube connector
3.5mm Bullet for end of tube - motor connector.
Battery PDB Distribution
Status | ||||
---|---|---|---|---|
|
How are batteries going to be arranged in series/parallel?
Scuffed diagram that needs explanation of potential implementation for three 12S batteries
How will our board support this layout?
Thoughts:
2 PM02D’s (2 banks of batteries), parallel after. Potentially on either side of the battery.
Junction point closer to the edge of the board (away from the pixhawk).
Airside Electrical Layout
Status | ||||
---|---|---|---|---|
|
Status | ||||
---|---|---|---|---|
|
Status | ||||
---|---|---|---|---|
|
Where each component goes needs to be added to the architecture document.
Need selection of proper wire gauges, types, etc.
For Battery connections, 8 AWG can be used to handle 75A continuous (maybe a little lower if stranded)
Stranded likely needed in order to have the required flexibility
Two power modules in parallel, two banks of batteries in parallel.
For motor connections, each motor draws around 15A (determined when discussing MT-30s)
14 AWG wire (24A) should be enough for ESC connections to PDB
Wire gauge for sensors
Crimpers