Ryan Scomazzon (onsite)
Meghan Dang (offsite)
Project managers
Kenny Na: Eclipse PM
Nolan Haines Ahmed Osman: Tracking antenna w ELRS
Andrew Chai (offsite) TBD
If you have been around for a term or so and are interested in being PM, reach out and we can get you involved! Could be higher commitment or just leading a bigger project.
We got lots we can do
https://forms.office.com/Pages/ResponsePage.aspx?id=h1o6cprzIkqSRz_CQMATlnJ_8qERK-dMn1dJnIofYSJUNzUxRjc2T1BOWFI4U1ZSUlgyMDBBSFRHNy4u feedback/leadership interest
Meeting times
How does this time work?
Not too late to fill out https://lettucemeet.com/l/ROLvD
Work sessions
We typically do work sessions for things like harnessing and creating PCBAs
Probably wont start until next week
What times work for everyone? After flight tests?
https://lettucemeet.com/l/n7AK5
Note this is a time that will reoccur weekly
Might not do every week depending on interest and what needs to be done.
Can't do work session until done bootcamp
Can come and get help on the bootcamp during the work session ONLY IF you finished the safety training
Competition Interest Form
This MUST be considered if you want to go to competition
Comp is fun and I am jealous I didn't go last year.
We can only bring 10 people so we definitely can’t bring everyone
Wont hurt to fill out anyways.
Start of term board order
Date pending
Driven by Meghan Dang
Thoughts from people here?
Pick&Place machine
This exists in the SDC
No one is using it
Sahil was told he can use it if he wants to set it up
Since it is just collecting dust, we can probably convince them to take it
Needs someone who cares enough to drive it though
Sayan, Edson interested in setting up
Flight Test
What is a flight test?
Where do we go?
WRESTRC
Not mandatory but cool to see the drone in action.
Planned to be on Sundays this term
We go to Costco after 🌭🌭🌭
Last flight test
https://discord.com/channels/776618956638388305/1306721339750613063
2024-12-14 Pegasus 2 Manual Piloting Flight Test - Flight Tests - WARG
Plan was to test system for competition task 2
Found our planned landing solution would be too risky
Tuning was less stable than expected
Water tank was leaky
Mech problem, they are working on it
Batteries sagged too much in the cold. Hard for autonomy to collect cluster data.
Gonna have to find a solution for future flight tests
Next flight test
January 19th (This Sunday)
https://discord.com/channels/776618956638388305/1326631979805966432
Plan:
Autonomy cluster estimation test
Must be done bootcamp for flight tests
...
Brief overview of competition tasks
Last term the plan was to land on the barrel
At the end of term flight test, we realized the tuning is not reliable enough for this and if the drone clips the barrel, its ggs
Now we will be doing a winch that lowers the pump
A new pump is needed, servo will likely be controlled by Pixhawk. Worst case we do an single servo driver
1-2 servos needed
If someone wants to help with this you are welcome
Eclipse Updates
Figuring out what software to use for harness diagrams
Project Updates
In order of priority. These are the active design projects.
RPi Interface Rev C - Electrical - WARG (atlassian.net) Kenny Na Daniel Puratich
Motivation: Redundant C2 ELRS link for 2026 Pegasus over LTE
PDB for RPi 5 (CV device)
Completed and good to go for start-of-term board order
12S ESC - Electrical - WARG (atlassian.net) Ethan Abraham& Andrew Chai
Motivation:
Make our in house ESC tailored to the specs of our drone
Our current ESC’s are expensive and go out of stock quite often
Can reduce costs and produce in volume with a custom designed PCB
Layout needs very minor cleanup (99% done)
need to address some comments in the schem
Find suitable heatsinks and mounting strategy
Place board order and determine copper pour stackup
Maybe some more PDN sims
Will be on Jan 20th Board order
ELRS Redundant Diversity RX - Electrical - WARG (atlassian.net)Nolan Haines
...
12S Pre-Charge Controller ModuleRobert Tang Kevin Li
Motivation: Reduce in-rush current on high-capacitance boards (harming connectors)
Preliminarily completed
Motivation: Space-efficient custom ESC for 12V systems
Expected EOT W25 completion
Tracking Antenna Controller w ELRSAhmed OsmanNolan Haines
...
12V to 24V Boost Groundside Converter - Electrical - WARG Tim Gu
Motivation: We have 12V power supplies. Charge batteries faster by boosting this voltage.
High current means we might need to do off the shelf instead
Looking into options to buy it instead
Gonna look at math
Look on facebook marketplace?
Water System Controller rev 2 - Electrical - WARG Shawn Yang
Motivation: Add current sensing to water pump controller for Pegasus Task 2
Expected Jan. 20th completion
Action Items
Look into Pix current limits
Look into new projects: BMS, PDB etc…
Follow up un redundant rx
Make thread for board order and discuss chinese new year