Attendance

Mechanical

Notes on manufacturing status.

Airframe

  • Fuselage status?

    • STATUS: Panels cut & mounted?

      • not cut yet, but outlines traced and ready to be cut next work session or time @.sohee is on campus

    • Will be done this weekend

  • Airframe is finalized, apart from maybe some slots that need to be milled into spars and tail boom if EE would like them

Wing

  • STATUS: Lasercut ribs

    • Task for laser cutting will be given out shortly after meeting

  • STATUS: 3D prints

    • All parts ready to print, will get those going

  • STATUS: Manufacturing tasks given out?

    • Split into two sections: frame and wrapping

    • Frame: will be done by this weekend

    • Wrapping: will be done in 1 or 2 more work sessions (so by Feb 8)

  • Timeline: initial prototype within 2 weeks (~ Feb 8), bit more for maiden flight

    • UPDATE: still on target?

      • Timing is looking good

landing gear

  • STATUS: Bent and wheels mounted?

    • Waiting on one sheet metal part. Should be ready first weekend of february

    • placed ordered for the servo adapter for rear landing gear today

  • Timeline: within next couple of weeks (~ Feb 1)

    • UPDATE: depends on order shipping, tentative ddl Feb 1

Empennage

  • STATUS: linkages for the elevators and rudder

    • task assigned to Rohaan who’s on-site

  • STATUS: need to 3D print the elevator and rudder

    • wasn’t 3D printed this weekend, planning for this weekend or earlier

  • Timeline: within next couple of weeks (~ Feb 1)

    • UPDATE: still on target?

      • yes

Everything Mech is in last drawer in the red toolbox.

Avionics/EE updates

  • Electrical Component status?

  • WARG PCB BOM: Eclipse maiden flight BOM

    • single servo driver x 2

    • can splitter x 3

    • 6s servo module x 1

    • 6s power module ?

    • Redundant 5V buck x1

image-20241107-011813.png
  • STATUS: Redraw block diagram

  • Jerry Tian will upload new block diagram after meeting

  • Harness timeline

    • Jerry Tian will host a session to familiarise more EE members with this

      • Tentative Feb 23

  • 6s Servo Module (EFS)

    • STATUS?

  • 6s power module (EFS)

    • STATUS? (last week said we would set due date)

  • EE to finalize and order connectors

Timeline

  • Foam Plane Pilot Training (first flight): Feb 2

  • Ecplise Strapdown Test: March 1st/2nd

  • Eclipse Maiden Flight Test: March 8th/9th

Pilot Training - Foam Plane

  • Mechanical structure is done, just need to mount electronics (this will hopefully change before tuesday meeting)