https://uwarg-docs.atlassian.net/wiki/x/J4Bbm
Attendance
Mechanical
Notes on manufacturing status.
Airframe
Fuselage status?
STATUS: Panels cut & mounted?
Wing
STATUS: Lasercut ribs
STATUS: Manufacturing tasks given out?
Timeline: initial prototype within 2 weeks (~ Feb 8), bit more for maiden flight
UPDATE: still on target?
landing gear
STATUS: Bent and wheels mounted?
Timeline: within next couple of weeks (~ Feb 1)
UPDATE: still on target?
Empennage
STATUS: linkages for the elevators and rudder
task assigned to Rohaan. Smile needs to follow up w/ him this week
STATUS: need to 3D print the elevator and rudder
wasn’t 3D printed this weekend, planning for this weekend or earlier
Timeline: within next couple of weeks (~ Feb 1)
UPDATE: still on target?
Avionics/EE updates
Electrical Component status?
WARG PCB BOM: Eclipse maiden flight BOM
single servo driver x 2
can splitter x 3
6s servo module x 1
6s power module ?
Redundant 5V buck x1
STATUS: Redraw block diagram
Question: are we gonna use the GPS listed here? https://uwarg-docs.atlassian.net/wiki/spaces/ARCHS22/pages/2556133415/Fixed+Wing+2025#Electrical-Components In the old (Jun 2024) block digram, it’s connected to the CAN splitter but It doesn’t seem to support CAN?
do we need 2 pitot tubes?
Harness timeline
Jerry Tian will host a session to familiarise more EE members with this
Tentative Feb 23
6s Servo Module (EFS)
STATUS?
6s power module (EFS)
STATUS? (last week said we would set due date)
Timeline
Foam Plane Pilot Training (first flight): Feb 2
Ecplise Strapdown Test: March 1st/2nd
Eclipse Maiden Flight Test: March 8th/9th
Pilot Training - Foam Plane
Mechanical structure is done, just need to mount electronics (this will hopefully change before tuesday meeting)