Sections for requesting team to fill out:
Admin preparation
Test Cards / Test Plan
Mandatory Attendees
Sections for flight test coordinator to fill out:
Flightline team
Location
Status
Drone
Sections for flightline team to fill out:
EFS to fill out Card #1, #2, #3 (Opflow, Tracking Antenna, Obstacle Avoidance)
đ Admin Preparation
Your status should read âsubmittedâ when you submit the FTR to our Flight Test Coordinator.
Once the coordinator approves, and a date/location/drone has been assigned, the status will change to âwaiting for sub team reviewâ. Once all sub-teams have reviewed and signed off, the status will change to âapprovedâ
Requested By | |
---|---|
Sub-Team Review (To be checked once reviewed by sub-team representative) |
|
Date of Request | Jan 16, 2024 |
Goal Summary |
|
Status? | WAITING FOR SUB-TEAM REVIEW |
Desired Airframe | Houston / Pegasus |
Location + Time | WrestRC 1300-1800 |
âď¸ Wx
https://www.windy.com/station/ad-cykf?42.541,-80.379,8 Waterloo Weather Station
đĽ Testplan - to be filled out by requesting team
Create ONE table per test-item. Eg: âLanding pad images over asphaltâ, âlanding pad images over grassâ, âlanding pad images over grass, highâ should all be unique tables.
Use each expand to capture one series of tests, eg âLanding pad detectionâ or âAuto-tuningâ.
Necessary Preparation
Explain what capacity you need, what needs to be mounted, etc.
Mechanical
- Pegasus cleared to fly (mechanically)
- sensor mount ready
- Motors + frame rigid
- Houston cleared to fly (mechanically)
- sensor mount attached
- arms + plates rigid
Electrical
- Pegasus cleared to fly (electrically)
- harnessing secure
- Houston cleared to fly
- Harnessing secure
- ELRS RXâs secure.
Embedded Flight Software
- Pegasus Ardupilot Configuration ready
- Opflow â Offsets correct, usage correct ? (EKF3?)
- Lidar â Offsets correct, usage correct? Height limits set?
- Houston Ardupilot Configuration ready
- Failsafes configured (Radio, GCS, Battery, ETC?)
- 360 Lidar â Configured, ground tested. Distances set properly?
- Test area SME available
- Test procedure is clear â Houston & Pegasus
- Possible deviations from test understood and considered â Houston & Pegasus
- Software ground tested
- Ground tests complete on all airframes (on battery over telemetry)
- Tracking Antenna
- Tested ? SME ready?
- ELRS / Radio management correct.
- ELRS rxâs on houston & pegasus. â Clear unique models.
- ELRS Airport on houston â Verify functioning.
- RFD900x on Pegasus â Verify functioning
- ELRS Trainer â Verify functioning
Autonomy
- LTE telemetry ready
đŤ Attendees
This is a section for all attendees from your subteam which will be present for this flight test. (because they are testing their products, or otherwise)
Name | Phone # (opt) | Sub-team | Driving | Role |
---|---|---|---|---|
Director | Y - 5pass SUV | |||
Director | 5-person liftback | |||
Mechanical | ||||
Mechanical | ||||
This section and remaining to be filled out by FTC and Flightline Team
Flightline Team
Name | Phone # | Role | Reason |
---|---|---|---|
Pilot | ;/ | ||
Pilot |
Pre-Flight Preparation
Checklists
Incident Procedures
â˛ď¸ Flight Test Timeline
Date/Time | Action | Notes |
---|---|---|
0700 | Start charging batteries 4x 6s 5000mah (pegasus) 3x 3s 4000mah (houston) | |
0800 | Begin checklists | |
0900 | Briefing @ WARG Bay | |
0930 | Begin loading vehicles | |
1000 | Arrival at Flight Test Location | |
1030 | Flight Test Card #1 + 2: Opflow calib. | |
1030 | Flight Test Card #3: Houston obstacle avoidance | |
1200 | Packup | |
1230 | Lunch | |
1300 | Debrief | |
<> |