General notes/questions
Must be done before the flight test (Saturday May 18th)
requirement somewhat dropped but target is before comp to show the judges
Prior to competition for 2024 system diagram ← will be changed after comp
Is mounting on Pegasus 2 viable? Smile Khatri
Confirmed Yes this is the best path forward
Which pattern would look best? Nathan Green Emma Chan
All White
When is the assembly + photoshoot?
Assembly Saturday or Sunday Smile Khatri Parker Lawrence-Valeriani
Bring as many people as possible
Photoshoot Monday, (Tuesday worst case scenario) Emma Chan
What needs to be done:
MECHANICAL + ELECTRICAL (ASSEMBLY SESSION)
Task | Department | Status | When |
---|---|---|---|
Soldering wires on boards & disconnecting headers | Electrical | Saturday (2024.05.18) or Sunday (2024.05.19) | |
Mounting boards on motors & running wires | Mechanical + Electrical | Saturday (2024.05.18) or Sunday (2024.05.19) | |
Landing gear full assembly | Mechanical | Saturday (2024.05.18) or Sunday (2024.05.19) | |
Final checks | Mechanical + Electrical | Saturday (2024.05.18) or Sunday (2024.05.19) | |
Disassemble | Mechanical | Tuesday (2024.05.21) |
The boards will be connected to a 3S battery through a buck converter (Project 12V-5V @ 3A Buck Converter Board 2022 (altium.com)) dropping it to 5V
Should follow the following schematic
Should follow the following wiring diagram
Mounting should look like this
EFS
Kelvin Feng Eric Su Richard Dong
Task | Status | Deadline |
---|---|---|
Flash the firmware with an all white pattern | Done | (2024.05.17) Friday EOD |