📋 Admin Preparation

Requested By

Yuchen Lin Evan Janakievski Maxwell Lou

Goal Summary

test autonomy system, the cluster estimation

Status?

DRAFT / SUBMITTED / WAITING FOR SUB-TEAM REVIEW / APPROVED

Desired Airframe

Houston

Date(s)

19th Jan 2025

🥅 Test plan

Flight Card 1

Cluster estimation test

Pilot: Evan Janakievski

GSO: Yuchen Lin

What is being tested?

  •  Autonomy cluster estimation accuracy

Hardware to be installed, items to bring, batteries, etc (change status to success when installed or plan for installing at flight test is done)

  • Houston Drone

  • 4 3s batteries

  • CV camera

  • Landing pad

  • Measuring tape

CLUSTER ESTIMATION TEST PROCEDURE (HOUSTON)

Procedure

Goals / Objectives

Knockoff criteria

  1. Setup

Get the script to run (either manually or auto start on bootup)

Script is not running

  1. Place and measure landing pad distance from drone power-on location

Know true value of the landing pad location and home location. Use phone GPS to determine landing pad locations as a backup.

 

  1. Hover above the landing pad and fly a few passes at 5, 10, 20m altitude

 

 

 

Necessary Preparation

Explain what capacity you need, what needs to be mounted, etc.

Necessary items:

  • CV Camera on Houston

  • 4 3S batteries

  • 2 landing pads

  • measuring tape

Flight characteristics needed:

  • Flight speed

  • GPS

Comms / Support needed:

  • Autonomous/repeatable missions

  • ability to hold location within +/- X meters

  • FPV Video from the drone?

  • etc….

🫂 Mandatory Attendees

This is a section for all attendees from your subteam which will be present for this flight test. (because they are testing their products, or otherwise)

Name

Phone #

Sub-team

Role

Yuchen Lin

6474256385

Flight Test

  • coordination


Flightline Team

Name

Phone #

Role

Reason

Yuchen Lin

 

 

 

Pre-Flight Checklists

 Week-Before checklist
  • Software configuration correct

  • Compare against latest baselines and verify no params changed, or changes approved by comp-ft-team

  • LTE tested

  • Autopilot Orientation checked

  • Motors tested

  • Prop direction check

  • Sensors outputs healthy & within range

  • Controller input mappings correct

  • Controller input choices correct for pilot preferences

  • Wireless trainer tested & working per pilot preferences.

Hardware (wiring)

  • Wires are not too tight or too loose (comfortable, not strained, not flapping around)

    • No cut/exposed wires

    • Shrouding is neat + presentable

    • Solder joints look good

      • no cracks

      • no corrossion

      • no exposed contacts (unless expected)

    • Specific requirement from Daniel Puratich

      • no exposed pad without solder on ESC caps

        • i did this on peggy 2

        • someone will need to do with peggy 1

      • ESCs all have a touch of hot glue to secure cap to board

    • Connectors fully plugged in

    • Connectors in good health

Hardware (airframe)

  • Bolts secure (nothing loose)

    • Carbon fiber not cracked

    • 3D prints not failing / crushed / cracked

    • No loose items

Hardware (groundstation)

  • ELRS Gemini tested & Working

    • Logging correct

    • Data looks correct

    • Control tower tested & working

  • Tracking antenna x2 (control + video) (mechanical)

    • Servos secure

    • Hardware (antennas) secure

    • No cracks/bends/chips in polycarb/aluminum

    • Gears / shafts look healthy

    • Grease if necessary

  • Tracking antenna x2 (control + video) (electrical)

    • Electrical components secure

    • Power delivery / signal wires secure, no cracks/corrosion/damage

  • Video System

    • goggles(?)

    • Monitors(?)

    • Video tower tested & working

  • Laptop w/mission planner configured correctly.

    • LTE Link tested working

Flightline Kit

  • Spare motors

  • Spare props

  • Spare tools

    • Metric allen keys

    • Socket set (question)

    • Pliers (flatnose + needle nose)

  • USB-C cable (short & long)

  • Soldering iron + heat shrink + spare cables

  • Power supplies for ground station computer

  • Ground station computer

  • Spare bolts

  • Radio Controllers

 Day-before checklist
  • Mission plan clear

  • flightline roles assigned

  • Communication hierarchy established

  • Incident procedures & roles in-place & briefed to all flightline team members

  • Timeline for day-of clear

  • Battery charging plan, equipment management plan clear.

  • Transportation clear

 Day-of checklist
  • Batteries in safety bag

  • Equipment

    • Zip tie

    • duck tape

    • label maker

    • Type c cable

    • ELRS Gemini

    • Saleae Logic Analyzer

    • charged WARG laptop

    • spare bag for small electronics

    • controller box

      • two controller

      • battery tester

    • VTX box

  • execute

Total 5 main system checked:

  • Power system(battery and connection)

  • Propulsion system(motor and propeller)

  • Controller system(Control links and ground station system)

  • Sensory system(sensors)

  • Video system (VTX)


  • Debrief

  • clean / store equipment if necessary

⏲️ Flight Test Timeline

note test 1 is competition task 1 and test 2 is competition task 2

Date/Time

Action

Notes


💻 DEBRIEF

Flight test debrief report