Attendance
Mechanical
Notes on manufacturing status.
Airframe
Fuselage status?
STATUS: Panels cut & mounted? (said would be done last weekend)
Panels are cut and ready to be mounted (planning to check how it fits with the wing/spars attached this weekend before fully mounting it)
STATUS: Airframe slots (Mech/EE discussion last week)
Wing
STATUS: Lasercut ribs (task was supposed to be given out last week)
STATUS: 3D prints
STATUS: Frame (should be done), Wrapping (progress update)
Timeline: initial prototype within 2 weeks (~ Feb 8), bit more for maiden flight
UPDATE: still on target?
landing gear
STATUS: (had some delays last week due to part orders and whatnot)
Timeline: within next couple of weeks (~ Feb 1)
UPDATE: depends on order shipping, tentative ddl Feb 1
Empennage
STATUS: linkages for the elevators and rudder
STATUS: need to 3D print the elevator and rudder
Timeline: within next couple of weeks (~ Feb 1)
UPDATE: still on target?
Everything Mech is in last drawer in the red toolbox.
Avionics/EE updates
Maiden flight Electrical block diagram needs one more check before harness work starts https://uwarg-docs.atlassian.net/wiki/spaces/ARCHS22/pages/2556133415/Fixed+Wing+2025#Maiden-Flight-Electronics-System-Diagram
Harness timeline
physical harness done by Feb 23
6s Servo Module
STATUS? (rev 2 pcb + efs update)
6s power module (EFS)
STATUS? (progress & setting deadlines)
STATUS: EE to finalize and order connectors
Timeline
Foam Plane Pilot Training (first flight): Feb 2
Ecplise Strapdown Test: March 1st/2nd
Eclipse Maiden Flight Test: March 8th/9th