Attendance

Mechanical

Notes on manufacturing status.

Airframe

  • Fuselage status?

    • STATUS: Panels cut & mounted? (said would be done last weekend)

      • Panels are cut and ready to be mounted (planning to check how it fits with the wing/spars attached this weekend before fully mounting it)

  • STATUS: Airframe slots (Mech/EE discussion last week)

Wing

  • STATUS: Lasercut ribs (task was supposed to be given out last week)

  • STATUS: 3D prints

  • STATUS: Frame (should be done), Wrapping (progress update)

  • Timeline: initial prototype within 2 weeks (~ Feb 8), bit more for maiden flight

    • UPDATE: still on target?

landing gear

  • STATUS: (had some delays last week due to part orders and whatnot)

  • Timeline: within next couple of weeks (~ Feb 1)

    • UPDATE: depends on order shipping, tentative ddl Feb 1

Empennage

  • STATUS: linkages for the elevators and rudder

  • STATUS: need to 3D print the elevator and rudder

  • Timeline: within next couple of weeks (~ Feb 1)

    • UPDATE: still on target?

Everything Mech is in last drawer in the red toolbox.

Avionics/EE updates

Timeline

  • Foam Plane Pilot Training (first flight): Feb 2

  • Ecplise Strapdown Test: March 1st/2nd

  • Eclipse Maiden Flight Test: March 8th/9th

Pilot Training - Foam Plane