\uD83E\uDD45 Goals

  • Review and finalize deadlines for different tasks relating to the IMACS project keeping in mind the dates for the competition simulations

  • Get available materials for integrating and testing different components

  • Note IMAC due max Feb 18

\uD83D\uDDE3 Discussion topics

Time

Item

Presenter

Notes

11:00

Computer Vision

Mihir, Additya

  • Filling in for Ethan

  • Receiver isn't complete, but it’s being done by EFS, ideally Tuesday this week

  • GUI status: Sample complete, just need to connect to information from drone. Updating GUI in real time needs to be worked on.

  • Need to develop timeline on integration Mihir Gupta

11:05

EFS

Additya

  • Zero Pilot status similar to CV, laminar OS driver needs to be worked on.

  • Air-to-ground telemetry

  • Mock test still to be completed. We need to clarify this task with EFS

11:10

Mech

absent

11:12

Electrical

absent

  • Mihir Gupta to talk separately

  • Tasks to complete: Telemetry emulator PCB, antenna connectors to ground station equipment