RPi Interface Rev C - Electrical - WARG (atlassian.net)
Daniel Puratich Project Manager, Principle Hardware Engineer
Siddharth Muralikrishnan Ahmed Osman Anthony Lazar Anthony Luo Shawn Yang
coming along, schem long in a week and layout in another week seems doable
LTE Breakout - Electrical - WARG (atlassian.net)
Canceled, now part of RPi Interface Rev C - Electrical - WARG (atlassian.net)
green tasks need to be done → need a lot of new components for this board, anyone is welcome to take them, but I actually need these done
Most components added to Library
12V -> 5V @ 4A Buck Converter + ELRS Board - Electrical - WARG (atlassian.net)
Kenny NaEngineer
Layout in progress ~ 1 week, will be ready for midterm board order
24V->5V @ 5 A Buck Converter Board - Electrical - WARG (atlassian.net)
Schematic is under review by Kevin
Robert TangEngineer
Kevin Li PM
Placement almost completed
Will be ready for midterm board order
Unified Video System - Electrical - WARG (atlassian.net)
Tom Chiu Individual Contributor
Layout revamped
New stackup will be
L1 - SIG/PWR
L2 - 2 signal traces, but otherwise, all GND
L3 - Uninterrupted GND
L4- SIG/PWR
Rerouted all signal traces on top and bottom layers with many via transitions. 2 signal traces remain on L2
I tried to ensure that the 2 traces on L2 did not lose gnd reference signal traces do not lose reference.
Removed 2 decoupling caps on the buck to save space.
Sourced a smaller linear regulator for the 12V-5V step down to save space as the current one is overkill based on the required power draw from it.
Please review whenever possible!
Worked with Jerry to understand the existing VTX system. Helped a bit with installation and creating the harness for PWM signal from pixhawk to lumenier switch board.
12S ESC - Electrical - WARG (atlassian.net)
Ethan Abraham Individual Contributor
Schematic nearly complete. Need to change MCU pinout to abide by AM32 hardware groups
Looking for a somewhat experienced EE to handle/help me with layout
ELRS Redundant Diversity RX - Electrical - WARG (atlassian.net)
Nolan Haines Individual Contributor
Schematic completed, starting placement
Doesn’t need help but might later with routing
Sensor Cluster - Electrical - WARG (atlassian.net)
Schematic done, implementing some schematic feedback from Daniel
So far no one else has left any schematic comments
Going to start layout likely this week
Pegasus wiring documentation
https://github.com/UWARG/hardware/tree/master/Harness schematic is here
...
Needs Assessment (comparing to the manual test procedure we have rn):1. characterize our custom buck converter’s performance.2. understand our designs more, help ee members learnLoad transient test is helpful on identifying issues if downstream board is brownout during flight testKnowing efficiency of the bucks
3. efs running out of work to do
Jerry’s is too busy to work on this rn, will be on hold until he is more free
Action Items
This section is here for completeness. If a new task is assigned in a meeting, it will be added here. Jerry Tian will try to fix hot air gun, if not successful, he will write email to hakko for help