Change Description

ICARUS IMACs

GS Vrx Power

Daniel Puratich

daniel.puratich@uwaterloo.ca

Description of Change

Adding definition for how the groundstation video receiver module tower will be powered.

There are a handful of options for powering this device which may or may not be placed on a long pole and held in the air. Any of these options could be diode ORed (with actual diodes or an ideal diode ORing circuit) together if we so desired though this is a lot of extra effort for not that much pay off. These options are as follows and we can go with any of these options at competition depending on how things go:

  • 120VAC extension cable runs up the tower and then a standard 12VDC power supply powers the unit

    • extension cable at 120VAC used to avoid voltage drop over long 12VDC wire

    • Power is promised by competition organizers, though I guess we’re worried about possibly tripping the cable

    • We may not have extension cables long enough

  • In order of preference the groundstation video receiver tower will be powered by one of the following options at a time:

    1. Using a LiPo battery with a voltage in excess of 15VDC & a stepdown

      • This could be a 5S battery (which we have) or two 3S batteries in series (which we have for Houston)

      • Stepdown handled by End User Guide

    A single 3S battery and a COTS buck-boost

    Would require purchasing a buck-boost pcba
      • The disadvantage of this is battery life time

    1. 120VAC extension cable runs up the tower and then a standard 12VDC power supply powers the unit

      • extension cable at 120VAC used to avoid voltage drop over long 12VDC wire

      • This disadvantage of this is this power source may not be available in some cases and extension cables will be required

    Implementation

    See above.

    Reason for Change

    Clarity.

    Priority

    Medium

    Impact of Not Responding to Change

    Confusion

    What Groups, People, Sub-teams Need to be Notified?

    • Anni

    • Ethan

    • Michael

    • Nolan

    • Farris

    • Daniel

    • Aidan


    Change Impact

    Additional Parts/Resources Required and Costs

    • Extension cable option

      • Ordering an extension cable

    • stepdown option

      • Making harness for 3S series

      • Assembling more boards so we ensure we have spares (we have the components for this already)

    • buckboost option

      • Ordering COTS buck boost board

    Impact on deadlines

    Most of the work here is discussion.

    Alternatives and Recommendations

    Any other alternatives will be added above following discussion.

    Comments

    NA



    Change Request Sign Off

    Status

    ✅ Accepted / ⏸️ On Hold / ❌ Rejected / (question) More info Requested

    Comments

    Signatures/Name