Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Current »

Change Description

ICARUS IMACs

GS Vrx Power

Daniel Puratich

daniel.puratich@uwaterloo.ca

Description of Change

Adding definition for how the groundstation video receiver module will be powered.

There are a handful of options for powering this device which may or may not be placed on a long pole and held in the air. Any of these options could be diode ORed (with actual diodes or an ideal diode ORing circuit) together if we so desired though this is a lot of extra effort for not that much pay off. These options are as follows and we can go with any of these options at competition depending on how things go:

  • 120VAC extension cable runs up the tower and then a standard 12VDC power supply powers the unit

    • extension cable at 120VAC used to avoid voltage drop over long 12VDC wire

    • Power is promised by competition organizers, though I guess we’re worried about possibly tripping the cable

    • We may not have extension cables long enough

  • Using a LiPo battery with a voltage in excess of 15VDC & a stepdown

    • This could be a 5S battery (which we have) or two 3S batteries in series (which we have for Houston)

    • Stepdown handled by End User Guide

  • A single 3S battery and a COTS buck-boost

    • Would require purchasing a buck-boost pcba

Implementation

See above.

Reason for Change

Clarity.

Priority

Medium

Impact of Not Responding to Change

Confusion

What Groups, People, Sub-teams Need to be Notified?

  • Anni

  • Ethan

  • Michael

  • Nolan

  • Farris

  • Daniel

  • Aidan


Change Impact

Additional Parts/Resources Required and Costs

  • Extension cable option

    • Ordering an extension cable

  • stepdown option

    • Making harness for 3S series

    • Assembling more boards so we ensure we have spares (we have the components for this already)

  • buckboost option

    • Ordering COTS buck boost board

Impact on deadlines

Most of the work here is discussion.

Alternatives and Recommendations

Any other alternatives will be added above following discussion.

Comments

NA



Change Request Sign Off

Status

✅ Accepted / ⏸️ On Hold / ❌ Rejected / (question) More info Requested

Comments

Signatures/Name

  • No labels