🍍 Updates this week!
Admin
No work session this weekend
Push wiring diagram project (we want to start assembling electrical at end of the term/beginning of next term)
Last EE meeting for the term
Active PCB Projects
High Current Power Module (Zen, Chris)
Updated 12V buck based on feedback. Finished component selection for 5V buck.
12S ESC (Ethan, Chris)
6S ESC (Mena, Rayyan)
Rayyan: Continuing to go through datasheets to source passives
LED Controller (Neel, Parker)
Finalizing the block diagram tonight.
ELRS Gemini (Michael, Farris)
Michael
No real progress this week from me
PDB (Tom)
Michael Botros needs to check in with Tom
Tracking Antenna (Nolan, Hardy, Rukshi)
12S Servo Module (Stanley, Jack, Jerry)
Stanley: Selected new input capacitors, added new components to to Altium project, (had to download and modify footprints for Al poly, and 2220 caps, please look over them)
Bootcamper Progress Updates
No bootcampers currently