Attendance

Mechanical

  • Motor and propellers have arrived.

  • Manufacturing started last week. The progress so far:

    • All plates for the frame have been waterjet

    • Finished few stand-offs for the frame + 1 wing-spar

  • Plan for this weekend:

    • Waterjet the landing gear and a motor mount

    • Finish the second wing spar and tail boom (should be achievable this Saturday)

  • Empennage design complete, balsa sheets, and wooden dowels need to be procured (that’ll happen this week)

    • using 2 servos for the elevator, 1 servo for the rudder. They have arrived.

  • Wing manufacturing timelines

    • Could we get started on 1 of the wings this weekend since the spar is done? - Smile

    • Nathaniel:

      • Been busy with some school stuff recently but the only thing blocking wings are the ailerons

      • We could manufacture some ribs and 3d prints for the spacers but assembling should be held off

      • Will order more balsa

Avionics/EE updates

  • What is readiness of all of the following boards!

image-20241107-011813.png
  • 6S Servo module

    • coming in sometime this week, assembly not until next term unless otherwise requested

    • aiming for bringup + validation early next term

  • Redundant 5v buck

    • ordered and will be assembled and validated by EE co-ops this term.

  • single servo driver

    • firmware stuff?

  • do we want LED controller Rev 4 on this?

  • more details on wiring the airframe

    • do we have all the components needed?

    • Jerry Tian for interest in creating harness diagrams

    • is there a diagram for this + locations on the airframe?

  • Will select an Eclipse EE pm at the start of next term, might gauge interest soon.

Timeline

Piloting

  • Jerry

  • Manasva