phonenix | FW do crash tests, be able to replace the legs Mech team doing recap didn’t do altitude hold timeline is behind schedule, but at least a flight, July 8th for pid tuning, delayed because of midterm, and boards. buying something off the shelf instead of ordering custom ones? (not a good idea)
|
ZP3 | schematic almost done schematic review ongoing do we want to USB to be on the board? (probably no, whatever is easiest) deadline: Sept 1st, 5 boards. fw is mostly on neucleo, needs to be ported to new ZP3 PCB, estimated to take 2 days to 2 months (lmao) need ppl to solder/assemble ZP boards (we might now have enough people) (recruiting season as well)
|
IMACS | Timeline required setup for ground station hardware All flight stuff into the box video, transmitter and receiver, controls NO video link setup, waiting for funding, Readymade RC, antenna, due mid Oct.