Mechanical
Manufacturing status?
all current parts can be found at the bottom drawer of the red tool box
airframe
Main frame is assembled w/ the motor mount on as well
Fuselage to be done within 2 weeks. Only thing left is to cut the panels and mount it
wing
Both wing spars have been milled
Haven’t lasercut the ribs yet
Will be giving out tasks for manufacturing at this week’s mech meeting
Timeline: initial prototype within 2 weeks (~ Feb 8), bit more for maiden flight
landing gear
Sheet metal parts are ready, needs to be bent and wheels need to be mounted
We have the rear wheel servo in the Bay, there should be a connector in the Bay, it was ordered last term
Someone in person see if servo mount is in the bay
Timeline: within next couple of weeks (~ Feb 1)
empennage
Both vertical and horizontal stabilizers have been manufactured
Need to make the linkages for the elevators and rudder
plan to use the thin steel rods at the back shelf, like the same mechanism as foam plane
Need to 3D print the elevator and rudder
Timeline: within next couple of weeks (~ Feb 1)
Avionics/EE updates
Electrical Component status?
WARG PCB BOM: Eclipse maiden flight BOM
single servo driver x 2
can splitter x 3
6s servo module x 1
6s power module ?
Redundant 5V buck x1
Maybe redraw block diagram?
One for how it looks initially
Additional ones for further systems
Describe connectors used
Jerry will make a new one
Harness timeline?
BOM to track where things are
Harness diagram with lengths following mech finalization
@Jerry Tian will host a session to familiarise more EE members with this
Tentative Feb 23
6s Servo Module (EFS)
System testing is done, needs to be cleaned up
Will try to get it done before midterms
6s power module (EFS)
not started, people assigned and have plans for progress
being pushed hard this term
no date yet, will get back on that next week
Timeline
Foam Plane Pilot Training (first flight): Feb 2
Strapdown Test: March 1st/2nd
Maiden Flight Test: March 8th/9th
Derive Maiden Flight date
Check asana
Pilot Training - Foam Plane
mechanical structure almost done
next step is to add electronics