Major Milestones and Timeline - Winter 2022
Major Milestones and Tasks
Attitude Manager
Re-architecture (Code) - by Jan 15th
Controls input mixing - by Jan 20
PID Testing and Tuning - by mid-Feb
FW-CV Comms
Integration into Telemetry manager - by end January
Driver Development - by early Feb / late Jan
VectorNav VN-300 -
Other driver validation (Ultrasonic) -
XBee Communications - by end-January
Interchip Communications - by late January
Path Manager Re-Architecture - late-Feb, early March
2021 Milestones and timeline
Overall System Architecture (October-November)
PM
Waypoint Manager
Auto-taxi/takeoff/landing
Simulation
FreeRTOS Integration