2025-01-26 Tracking Antenna + Gemini Tx Planning Meeting
this board is gonna be basically copy paste of tracking antenna + gemini
Not many schematic based tasks
Delegate tasks for layout by breaking the board into subsections with minimal connections
different power architecture
Maybe make a general PDB to be used here? - Gonna ask Andrew since he was considering it for a project
We need Gemini Tx fully validated before we start throwing it on to here, in case schem changes need to be made
Nolan for architecture
Osman to drive deadlines
Gonna order parts to validate current boards
Do power analysis in the meantime
Look into where we need to buy TX modules - will delay if its from Aliexpress
Action Item | Tentative Timeline | Actual Timeline (date compeleted) |
---|---|---|
Order TX modules | Jan 27 |
|
Order components for testing ELRS Gemini | Jan 30 |
|
Worksesh for changing and testing board | Pending dates from order |
|
Power analysis done | Jan 31 |
|
Block diagram complete | Mon Feb 3 2025 |
|
Schematic complete | Feb 12 |
|
Assign layout tasks | After reading week |
|
Regular meetings
Every Sunday 2pm