2024-04-22 Battery Information
Summary
@Omar El-Sawy Driving progress
Led by @Nolan Haines
Four batteries locked in by technical director, placement one per side as drawn below.
Technical Details/Changelog
Schematic to Follow:
Layout:
Things TODO
do not delete any of these todos until approved by eelead
determine wire lengths add info to diagram
make a seperate “schematic” and “layout” drawing.
Get approval before cutting the wires for the lengths from @Nathan Green
the wires are expensive and this is the only set we have.
then we can follow this in assembling the second harness
soldering example given by stuff in soldering
@Daniel Puratich to complete a formalized nice public video
in meantime gain access to the folder using https://uwarg-docs.atlassian.net/wiki/spaces/AD/pages/2241790526 media ingest folder then you can see the raw data here
Assemble Second Harness for Peggy 2
approval from @Nolan Haines for this decision
Arch doc implementation Info
Diagrams to be merged in likely after competition
Approvals & Reviews
< space for reviewers to leave thoughts / approvals? >
Name | Approve/Deny? | Reason |
---|---|---|
@Nathan Green |
|
|
@Nolan Haines |
|
|